[1]何向红1,张 信1,程建华2.既有交通线上立交桥钢箱梁顶推施工技术[J].武汉工程大学学报,2015,37(06):36-41.[doi:10. 3969/j. issn. 1674-2869. 2015. 06. 008]
 ,Construction technology of steel box girder jacking based on existing traffic lines[J].Journal of Wuhan Institute of Technology,2015,37(06):36-41.[doi:10. 3969/j. issn. 1674-2869. 2015. 06. 008]
点击复制

既有交通线上立交桥钢箱梁顶推施工技术(/HTML)
分享到:

《武汉工程大学学报》[ISSN:1674-2869/CN:42-1779/TQ]

卷:
37
期数:
2015年06期
页码:
36-41
栏目:
资源与土木工程
出版日期:
2015-06-30

文章信息/Info

Title:
Construction technology of steel box girder jacking based on existing traffic lines
文章编号:
1674-2869(2015)06-0036-06
作者:
何向红1张 信1程建华2
1.长江工程职业技术学院,湖北 武汉430212; 2.中铁大桥局第七工程有限公司,湖北 武汉430056
Author(s):
HE Xiang-hong1 ZHANG Xin1CHENG Jian-hua2
1. Changjiang Institute of Technology,Wuhan 430212,China;2. The 7th Engineering CO., LTD., China Railway Major Bridge Engineering Group,Wuhan 430056,China
关键词:
主线高架桥 钢箱梁施工 分步顶推
Keywords:
main line viaduct steel box girder construction step-by-step jacking
分类号:
U445
DOI:
10. 3969/j. issn. 1674-2869. 2015. 06. 008
文献标志码:
A
摘要:
武汉市二环线武昌段接线工程梅家山立交桥钢箱梁项目属于既有交通线下高风险路段施工项目. 主线桥钢箱梁跨路施工过程中,采用现场情况分析、模型数据计算分析与试验测试等步骤,探索了既有交通线上钢箱梁顶推法施工工艺、临时工程设计布置等方法,形成了一套较为完整的钢箱梁连续顶推施工技术和安全操作技术要点. 运用该方法进行施工,桥下交通影响较小,施工干扰小,安全系数高. 确保了工程进度和施工质量,有效节约了施工成本.
Abstract:
The Meijiashan overpass steel box girder project at Wuchang section of Wuhan′s Second Ring Road is a high-risk road construction project on existing transportation line. Aimed at the across-road construction process of the main bridge steel box girder, the steel box girder pushing technology on existing traffic lines and the temporary engineering design layout were explored by analyzing the on-site situation, computing model data and test, the steel box girder jacking construction technology and the key points about safety operation were proposed. The practice proves that it has little effect on the traffic under the bridge and the construction process, which guarantees the project progress and the construction quality, and saves the construction cost.

参考文献/References:

[1] 陈晓桥,李华龙,鲜亮. 连续钢箱梁顶推结合支架法的施工[J].公路,2007(7): 42-45.[2] 刘建龙. 哈尔滨尚志大桥连续钢箱梁顶推设计与施工技术[J].公路工程,2005,30(1):110-112,129.[3] 张光桥,贾志坚.济南黄河三桥钢箱梁顶推施工工艺[J].公路,2008(12):114-117.[4] 贾建彬.高速公路跨线钢箱梁施工质量控制措施[J].交通标准化,2008(6):71-73.JIA Jian-bin.Quality control measures for construction of steel box girders of overpass expressways[J].Communications Standardization,2008(6):71-73.(in Chinese)[5] 赵鹍鹏,潘胜平.厦漳跨海大桥北汊斜拉桥墩顶区钢箱梁架设方案[J].桥梁建设,2012,42(5):109-113.ZHAO Kun-peng,PAN Sheng-ping. Erection scheme for steel box girder in pier top areas of cable-stayed bridge of north bridge of Xiazhang Sea-crossing Bridge[J].Bridge Construction,2012,42(5):109-113. (in Chinese)[6] 范翔,郁志刚,徐新华,等.跨沪宁高速公路钢箱梁顶推施工技术[J].城市道桥与防洪,2012(4):149-153.FAN Xiang, YU Zhi-gang,XU Xin-hua,et al. Construction techniques for incremental launching of steel box girderover Shanghai-Nanjing Expressway[J]. Urban Roads,Bridges & Flood Control,2012(4):149-153.(in Chinese)[7] 陈亚强.福州鼓山大桥钢箱梁顶推设计与施工[J].建筑技术,2010(7):670-672.[8] 徐文平,张宇峰.钢桥斜拉施工技术的探讨[J].公路,2007(5):77-78.[9] 杨雳,赵全治,杜民,等. 自锚式悬索桥钢箱梁拖拉法 施工技术[J].桥梁建设,2008(5):50-51.

相似文献/References:

备注/Memo

备注/Memo:
收稿日期:2015-04-24作者简介:何向红(1962-),女,湖北黄梅人,高级工程师,副教授. 研究方向:土木工程设计、监理与施工.
更新日期/Last Update: 2015-08-22