Title:
Ultrasonic Array Measurement and Key Algorithm in Monitoring of Immersing and Docking of Immersed Tube Tunnel
文章编号:
20170409
作者:
赵朋辉1柴修伟2*胡勇前1孙 斌3阎要锋2
1. 佛山新城建设开发有限公司,广东 佛山 528000;2. 武汉工程大学资源与土木工程学院,湖北 武汉 430074;3. 上海海科工程咨询有限公司,上海 200231
Author(s):
ZHAO Penghui1CHAI Xiuwei 2*HU Yongqian1SUN Bin3YAN Yaofeng2
1. Foshan New Town Construction Development Co. , LTD,Foshan 528000,China;2. School of Resource and Civil Engineering,Wuhan Institute of Technology,Wuhan 430074,China;3. Shanghai Heike Engineering Consulting Co. , LTD, Shanghai 200231,China
关键词:
沉管隧道超声阵列测量系统沉放和对接算法
Keywords:
immersed tunnelultrasonic array measurement systemimmersing and docking algorithm
分类号:
TU354
DOI:
10. 3969/j. issn. 1674?2869. 2017. 04. 009
文献标志码:
A
摘要:
水下高精度沉放对接是沉管隧道施工的一个关键环节,对测量方法的环境适应性和精度等指标要求很高. 目前实际工程中多采用高精度全站仪测量和刚性测量塔传递坐标的方法;此外,国外提出水下声呐测量方法,环境适应性强,且精度不随隧道长度增加而下降. 本文通过对水下声呐法进行创新改进,采用三点后方交会方法,提出超声阵列测量方法,并用于佛山汾江路南延线沉管隧道工程中管段沉放对接的测量监控试验,并将测量结果与高精度全站仪测量结果进行了对比分析. 现场监测试验结果表明,该方法能够满足工程需要,在管段间距2 m时,三轴坐标测量精度不大于± 45 mm.
Abstract:
The high precision immersion and docking is the key part in immersed tube tunnel construction,which requires better?environmental?adaptation and high accuracy to the measurement system. Now,the high-precision total station and rigid measurement tower are commonly used in actual engineering. Moreover,the sonar method is also proposed in foreign country,which has good adaption to the surrounding and its precision does not decline with the tunnel length increasing. Through innovation?and?improvement based on the underwater sonar methods,the ultrasonic array measurement system was proposed by the three points resection method and was used to measure and monitor the immersed tube tunnel immersing and docking process of Foshan Fenjiang road extending to the south. Compared with the high-precision total station,the method can meet?the?needs?of engineering,and the 3-axis measurement precision can be controlled between +45 mm and -45 mm when the distance between two tubes is 2 m.

参考文献/References:

[1] 潘永仁,丁美. 大型沉管隧道管段沉放施工技术[J]. 现代隧道技术,2004,41(5):1-5. PAN Y R,DING M . Techniques for sinking and jointing tube sections of large immersed tube tunnel[J]. Modern Tunneling Technology,2004,41 (5): 1-5. [2] 胡政才,先其明,马积薪. 日本多摩川沉管隧道的设计与施工[J]. 世界隧道,1995 (5):52-75.HU Z C,XIAN Q M,MA J X. Design and construction of tamagawa immersed tunnel in Japan [J]. World Tunneling,1995 (5):52-75. [3] 宁茂权,肖明清. 海底沉管隧道关键技术设计与分析[J]. 铁道工程学报,2008,119(8):50-57. NING M Q,SHAO M Q. Design and analysis of key technology about channel immersed tunnel [J]. Journal of Railway Engineering Society,2008,119(8):50-57. [4] 王朝辉. 内河沉管隧道浮运沉放施工技术[J]. 施工技术,2012,41(18):117-120. WANG C H.Construction technology of floating and sinking of immersed tunnel crossing inland river [J]. Construction Technology,2012,41(18):117-120. [5] 聂美琳译. 京叶台场隧道[J]. 世界沉管隧道技术,1998(5):41-85.NIE M L (Translated). Keiyo odaiba tunnel [J]. World Immersed Tunnel Technology,1998 (5):41-85. [6] RASMUSSEN N S. Concrete immersed tunnels-forty years of experience [J]. Tunneling and Underground Space Technology,1997,12(1):33-46. [7] GURSOY A. Immersed steel tube tunnels: an American experience [J]. Tunneling and Underground Space Technology,1995,10 (4):439-453. [8] 王解先,许琛,陆彩萍. 沉管沉放的实时监测[J]. 测绘学报,2002,31(增刊):70-72. WANG J X,XU C,LU C P. Real-time surveying of immersed tube allocation [J]. Journal of Geodesy and Geo-Information,2002,31(Suppl. ):70-72. [9] 潘永仁. 上海外环沉管隧道大型管段浮运方法[J]. 施工技术,2004,33(5):52-54. PAN Y R.The floating transport method of large elements employed for Shanghai out-ring immersed tube tunnel [J]. Construction Technology,2004,33(5):52-54. [10] 吴瑞大,方长远. 适合近岸管节水下施工的测量塔全站仪定位方法[J]. 中国港湾建设,2012(4):43-46. WU R D,FANG C Y. Positioning methods by total stations for survey towers suitable for near-shore underwater laying of tunnel sections[J]. China Harbor Engineering,2012(4):43-46. [11] 邓建林. 沈家门港海底沉管隧道浮运、沉放施工控制技术[J]. 隧道建设,2015,35 (9):914-919. DENG J L. Control technology for towing and sinking of immersed tubes: case study on Shenjiamen port sub-sea tunnel [J]. Tunnel Construction,2015,35 (9):914-919. [12] 郭建文. 海河隧道沉管沉放对接的主要施工技术[J]. 铁道标准设计,2013(4): 73-77. GUO J W. Key construction technologies of sinking and docking of immersed tube of Haihe river tunnel [J]. Railway Standard Design,2013(4):73-77. [13] 申琪玉,邱峰,张海燕. 广州洲头咀隧道管段浮运沉放关键技术研究[J]. 施工技术,2010,39(5): 15-17. SHEN Q Y,QIU F,ZHANG H Y.Research on key sinking technology of pipe sections in Guangzhou Zhoutouzui immersed tunnel[J]. Construction Technology,2010,39(5):15-17. [14] 任朝军,苏林王,吕黄,等. 声纳法在管节沉放实时定位测量中的应用[J]. 现代隧道技术,2012,49(5):132-135. REN C J,SU L W,L? H,et al. Application of the sonar method to real-time positioning measurement for an immersed element [J]. Modern Tunneling Technology,2012,49(5):132-135. [15] 郭禄光,樊功瑜. 最小二乘法与测量平差[M]. 上海:同济大学出版社,1984. [16] 田青文,刘万林. 控制测量学[M].西安:西安地图出版社,2004.